Question: Current Attempt in Progress In October, Pine Company reports 22,100 actual direct labor hours, and it incurs $118,500 of manufacturing overhead costs. Standard hours allowed

 Current Attempt in Progress In October, Pine Company reports 22,100 actual

Current Attempt in Progress In October, Pine Company reports 22,100 actual direct labor hours, and it incurs $118,500 of manufacturing overhead costs. Standard hours allowed for the work done is 23,700 hours. The predetermined overhead rate is $5.05 per direct labor hour. Compute the total overhead variance. Total Overhead Variance