Question: Current Attempt in Progress On February 1 , 2 0 2 3 , Wildhorse Contractors agreed to construct a building at a contract price of

Current Attempt in Progress
On February Wildhorse Contractors agreed to construct a building at a contract price of $ The total estimated
construction costs would be $ and the project would be finished in Information relating to the costs and billings for
this contract is as follows:
Calculate the gross profit loss that should be recognized for and using the percentage completion method. Enter
negative amounts using either a negative sign preceding the number eg or parentheses eg Round percentage
complete to decimal place, eg and final answers to decimal places, eg