Question: Current Attempt in Progress Pharoah Construction Company had a contract starting April 2 0 2 4 , to construct a $ 3 4 0 0

Current Attempt in Progress
Pharoah Construction Company had a contract starting April 2024, to construct a $34000000 building that is expected to be
completed in September 2025, at an estimated cost of $31300000. At the end of 2024, the costs to date were $14398000 and the
estimated total costs to complete had not changed. The progress billings during 2024 were $8240000 and the cash collected during
2024 was $5520000. Pharoah uses the percentage-of-completion method. For the year ended December 31,2024, Pharoah would
recognize gross profit on the building of
$2720000.
$1242000.
$0.
$1143371.
 Current Attempt in Progress Pharoah Construction Company had a contract starting

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!