Question: Current Attempt in Progress Presented below are data relating to labor for Verde Appliance Repair Shop. The desired profit margin per hour is $20. The

Current Attempt in Progress Presented below are data relating to labor for Verde Appliance Repair Shop. The desired profit margin per hour is $20. The material loading charge is 60% of invoice cost. Verde estimates that 4,400 labor hours will be worked next year. If Verde repairs a dishwasher that takes 1.6 hours to repair and uses parts of $90, compute the bill for the job. Total cost