Question: Current Attempt in Progress The following information is available for Sunlands Hot Dogs: Actual production 11,830 packages Budgeted production 12,500 packages Standard direct labor hours
Current Attempt in Progress
The following information is available for Sunlands Hot Dogs:
| Actual production | 11,830 | packages | |
| Budgeted production | 12,500 | packages | |
| Standard direct labor hours | 1.5 | direct labor hours per package | |
| Actual direct labor hours | 18,836 | ||
| Standard variable overhead rate | $3 | per direct labor hour | |
| Actual variable overhead costs | $47,648 |
Calculate the variable overhead spending and efficiency variances. (Round answers to 0 decimal places, e.g. 125. If variance is zero, select "Not Applicable" and enter 0 for the amounts.)
| Variable overhead spending variance | $enter the variable overhead spending variance in dollars | select an option Not ApplicableFavorableUnfavorable | |
|---|---|---|---|
| Variable overhead efficiency variance | $enter the variable overhead efficiency variance in dollars | select an option UnfavorableNot ApplicableFavorable |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts