Question: Current Attempt in Progress Wildhorse, Inc. began work on a $ 7 , 0 2 5 , 0 0 0 contract in 2 0 2

Current Attempt in Progress
Wildhorse, Inc. began work on a $7,025,000 contract in 2025 to construct an office building. Wildhorse uses the cost-recovery method. At December 31,2025, the balances in certain accounts were Construction in Process $1,854,000, Accounts Receivable $219,000, and Billings on Construction in Process $945,000.
Indicate how these accounts would be reported in Wildhorse's December 31,2025, balance sheet. (List assets in order of liquidity.)
WILDHORSE, INC. Balance Sheet
$
$