Question: Current Attempt in Progress Windsor Company's standard labour cost per unit of output is $22 (2 hours x $11.05 per hour). During August, the
Current Attempt in Progress Windsor Company's standard labour cost per unit of output is $22 (2 hours x $11.05 per hour). During August, the company incurs 2,100 hours of direct labour at an hourly cost of $10.75 per hour in making 1,000 units of finished product. Calculate the total, price, and quantity labour variances. (Round per unit calculations to 2 decimal places, eg. 1.25 and final answers to O decimal places, e.g. 125.) Total labour variance $ Labour price variance $ Labour quantity variance $ Favourable Unfavourable Neither favourable nor unfavourable