Question: Custom Carpentry provides bespoke carpentry services. Each project takes approximately 40 hours. The company anticipates 200 projects annually. They have invested $1,200,000 in their facilities
Custom Carpentry provides bespoke carpentry services. Each project takes approximately 40 hours. The company anticipates 200 projects annually. They have invested $1,200,000 in their facilities and expect an ROI of 18%. The budgeted costs for the coming year are shown below:
| Cost Item | Per Project ($) | Total ($) |
|---|---|---|
| Direct Materials (Wood, etc.) | 100 | 20,000 |
| Direct Labor (Carpenters) | 200 | 40,000 |
| Variable Overhead | 50 | 10,000 |
| Fixed Overhead | - | 180,000 |
| Variable Selling & Admin Expenses | 30 | 6,000 |
| Fixed Selling & Admin Expenses | - | 54,000 |
Required:
- Calculate the total cost per project.
- Determine the desired ROI per project.
- Compute the target price per project.