Question: Custom's has three cost pools and an associated cost driver to allocate the costs to the product. The cost pools, cost driver, estimated overhead, and

Custom's has three cost pools and an associated cost driver to allocate the costs to the product. The cost pools, cost driver, estimated overhead, and estimated activity for the cost pool are as follows: Estimated Activity Estimated per Driver Overhead Cost Pool Cost Driver Material Material Requisitions 13,000 $49,400 Machining Machine Hours 186,500 363,675 Inspection Number of Inspections 8,000 60,800 What is the predetermined overhead rate for each activity? Round your answers to two decimal places. Predetermined Cost Pool Overhead Rate Material per requisition Machining per machine hour Inspection per inspection