Question: Cut Bread: 7 2 0 units / hour Spread Mayo: 1 2 0 units / hour Add Turkey: 1 8 0 units / hour What

Cut Bread: 720 units/hour
Spread Mayo: 120 units/hour
Add Turkey: 180 units/hour
What is the flow rate if the demand rate is 100 sandwiches per hour?