Question: Cutoff Progress Date is Today and The Work Package Updates are : Planned Value for Your Work Package = Qr 75,000 QS Estimate the Work

Cutoff Progress Date is Today and The Work

Cutoff Progress Date is Today and The Work Package Updates are : Planned Value for Your Work Package = Qr 75,000 QS Estimate the Work had Been Done =Qr60,000 Accounts Give you the Cost Incurred =Qr.80,800 What is CV? A. +15,00 B. 15,000 C. 20,800 D. +20,800