Question: Cutoff Progress Date is Today and The Work Package Updates are : Planned Value for Your Work Package = Qr 75,000 QS Estimate the Work

Cutoff Progress Date is Today and The Work Package Updates are : Planned Value for Your Work Package = Qr 75,000 QS Estimate the Work had Been Done =Qr60,000 Accounts Give you the Cost Incurred =Qr.80,800 What is CV? A. +15,00 B. 15,000 C. 20,800 D. +20,800
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
