Question: CV TUMLIC urrent Attempt in Progress The following direct materials and direct labor data pertain to the operations of Culver Company for the Costs Actual

CV TUMLIC urrent Attempt in Progress The following direct materials and direct labor data pertain to the operations of Culver Company for the Costs Actual labor rate $14.50 per hour $112.00 perton Actual materials price Standard labor rate $11.50 per hour Standard materials price $114.00 per ton Quantities Actual hours incurred and used 3,720 hours Actual quantity of materials purchased and used 1,076 tons Standard hours used 3,890 hours Standard quantity of materials used 1,040 tons search wwww Compute the total, price, and quantity variances for materials and labor. Total materials variance $ -1952 Unfavorable Materials price variance $ -38736 Materials quantity variance $ Total labor variance $ $ TA Labor price variance $ Labor quantity variance
Step by Step Solution
There are 3 Steps involved in it