Question: D) $5.650.000 Question 6 For a project, the following eamed walue data have been assessed: AC: $4,000,000 CV: $500.000 SPI: 1.12 BAC: $9,650.000 What is

D) $5.650.000 Question 6 For a project, the
D) $5.650.000 Question 6 For a project, the
D) $5.650.000 Question 6 For a project, the following eamed walue data have been assessed: AC: $4,000,000 CV: $500.000 SPI: 1.12 BAC: $9,650.000 What is the Planned Value (BCWS) of the project at the time of the assesknient? A) $3.850.000 B) 53,500,000 C) 53,125,000 Di $3,750,000 $59,210$0,000$84,210$109,210 Euestion 8 A project was budgeted at $1,000,000 Meanwhile, the project is executed, and the followig current figures have been aismed pin $500,000 EV: $450.000AC$550,000 Assuming that the cost Varlance was caused by one-time cost divirs which are ne mare effective, what estimate at completion (faC) can you derive from theise figures? $950,000$1.000,000$1.050,000$1.100,000 Question 9 A project manager reported the following eamed value data. PY. 512,400000 EV. 514,500000 AC 514,500,000 Whut doet this mean

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!