Question: d . ( 6 % ) Assume each activity i costs Slope ( i ) day to reduce in duration by one day, and that

d.(6%) Assume each activity i costs Slope(i) day to reduce in duration by one day, and that each activity duration can only be reduced by a maximum of 1 day. How would you go about reducing the project duration by 3 days?