Question: + D An g g QUESTION 1 Based on the give data, please construct the project diagram and develop the optimal crashing solution and compute

+ D An g g QUESTION 1 Based on the give data,

+ D An g g QUESTION 1 Based on the give data, please construct the project diagram and develop the optimal crashing solution and compute the total crashing cost. Task Predecessors Normal Time (week) Crash Time (week) Crash Cost Per Week A Nil 12 7 400 B A 8 5 500 4 3 3,000 D B,C 12 9 7,000 E B,C 4 1 200 F E 4 1 X200 G D,F 4 3 7,000