Question: D = Average demand per period sD = Standard deviation of demand (forecast error) per period L = Average lead time - between when an
D = Average demand per period
sD = Standard deviation of demand (forecast error) per period
L = Average lead time - between when an order is placed and when it is received
sL = Standard deviation of lead time per order
Safety Stock (ss) = SQRT(LsD2+D2sL2) x "Z Score"
Cell-Phones-For-Less sells a large quantity of prepaid cell phones, on average 1500 per week with a standard deviation of 145. The lead time for the prepaid cell phones is five weeks with a standard deviation of two weeks. The owner continuously monitors inventory. Their typical order size is 4500 phones.
What safety stock should be held by Cell-Phones-For-Less to meet by a cycle service level (CSL) of 99%?]
Select one:
a. 4,500 phones
b. 8,225 phones
c. 7,032 phones
d. 3,018 phones