Question: ( d ) Consider the flownet shown in Figure Q 1 ( d ) below, with a cut - off wall underneath the concrete dam.

(d) Consider the flownet shown in Figure Q1(d) below, with a cut-off wall underneath the
concrete dam. The bulk unit weight of the soil is 19kNm3.
i. Estimate the coefficient of permeability of the soil if the measured flow rate (q) is
5.510-5m3s per unit length.
(2 marks)
(2 marks)
ii. Estimate the vertical effective stress at Point A.
(3 marks)
iii. Estimate the net water pressure at Point B along the cut-off wall.
(2 marks)
Figure Q1(d)