Question: D . N is a critical activity. E . S is a critical activity. Question 4 Which of the following statements regarding CPM networks is

D.N is a critical activity.
E. S is a critical activity.
Question 4
Which of the following statements regarding CPM networks is true?
Selected Answer:
D. If a specific project has multiple critical paths, all of them will have the same duration.
Answers:
A. There can be multiple critical paths on the same project, all with different durations.
B. The early finish of an activity is the latest early start of all preceding activities.
C. The late start of an activity is its late finish plus its duration.
D. If a specific project has multiple critical paths, all of them will have the same duration.
E. None of the above are true.
Question 5
Which of the following is not characteristic of a project?
Selected Answer:
D. Uses no resources
Answers:
A. has a life cycle
 D.N is a critical activity. E. S is a critical activity.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!