Question: D . N is a critical activity. E . S is a critical activity. Question 4 Which of the following statements regarding CPM networks is
D is a critical activity.
E S is a critical activity.
Question
Which of the following statements regarding CPM networks is true?
Selected Answer:
D If a specific project has multiple critical paths, all of them will have the same duration.
Answers:
A There can be multiple critical paths on the same project, all with different durations.
B The early finish of an activity is the latest early start of all preceding activities.
C The late start of an activity is its late finish plus its duration.
D If a specific project has multiple critical paths, all of them will have the same duration.
E None of the above are true.
Question
Which of the following is not characteristic of a project?
Selected Answer:
D Uses no resources
Answers:
A has a life cycle
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock