Question: d . Path Wiring - Software - Testing, 2 1 e . None of above If you crash this project to reduce the total time
d Path Wiring Software Testing,
e None of above
If you crash this project to reduce the total time by one day, which activity activities should you crash?
a
Design
b
Wiring
c
Chip install
d
Software
e
Testing
The minimum cost of crashing the following project by days is enter the additional crashing cost; enter your response as a whole number
What is the maximum number of days the project could be crashed?