Question: D Question 10 1 pts A project has the following cash flows set out below. What is the net present value of this project if

D Question 10 1 pts A project has the following cash flows set out below. What is the net present value of this project if the relevant discount rate is 2 percent? Enter your final answer to two decimal places. Year Cash flow 0 -1.556 1 519 2 2,071 3 3,072 Question 2 1 pts Which of the following is an advantage of the budgeting process? O It can force management to focus on the past and not be distracted by current activities of the organisation It can help facilitate goal congruence throughout the organisation. o It may lead to managers introducing budgetary slack. O It focuses on the needs of customers and ensures that they receive good service and high-quality products at a fair price