Question: D Question 19 1 pts Royce Consulting signed a contract with a new client for a short-term project that requires workers with a high level

D Question 19 1 pts Royce Consulting signed a
D Question 19 1 pts Royce Consulting signed a contract with a new client for a short-term project that requires workers with a high level of skill. Royce's employees are skilled and can do the work, but not within the scheduled timeframe. Which strategy would be best to avoid a short term labor shortage while retaining the ability to handle a complex project? retrain and transfer employees from other departments overtime hire new employ buy new technology impose a hiring free