Question: D Question 20 2 pts A CPI below 1.00 means The project is ahead of schedule The project is over budget The project is behind
D Question 20 2 pts A CPI below 1.00 means The project is ahead of schedule The project is over budget The project is behind schedule The project is under budget Question 21 2 pts If the project has been front-end loaded, and the SPI is 1.0 the true schedule would actually indicate: You are under budget You are right on schedule and budget You are ahead of schedule You are behind schedule