Question: D Question 25 1 pts SP Inc. recently completed a job order - Job P. The following data have been recorded on its job order
D Question 25 1 pts SP Inc. recently completed a job order - Job P. The following data have been recorded on its job order sheet: Direct materials Direct labor hours Direct labor wage rate Machine hours $3000 200 labor hours $30 per labor hour 600 machine hours SP applies manufacturing overhead based on labor hours. In other words, it uses a single-cost-pool system, with labor hours as the cost driver. The predetermined overhead rate is $40 per labor hour. Which of the following is closest to the total manufacturing cost that would be recorded on the job cost sheet for Job P? $33,000 O $17,000 O$9,000 O $24,000 O $11,000 O $10,200 $8,000 D Question 26 1 pts