Question: D raw the project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task 2.
Draw the project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task
2. List the tasks on the critical path
3. What is the expected project duration in weeks?
4. What is the slack for each activity?
A:B:C:D:E:F:
5. The project needs to be crashed by 2 weeks. What are the activities crashed to achieve the 2 week crash at lowest cost? List the new duration of each crashed task and any associated crash costs
ActivityDurationCrash Cost
A
B
C
D
E
F
6. Draw the NEW project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task
7. List the tasks on the critical path (0.4 pts.)

Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
