Question: Data flows from the Control Quality process to the: Question 1 0 options: Direct and Manage Project Work process. Control Scope process. Close Procurements process.

Data flows from the Control Quality process to the:
Question 10 options:
Direct and Manage Project Work process.
Control Scope process.
Close Procurements process.
Develop Project Management Plan process.