Question: Data for a project is shown below: Activity Duration (months) Precedence Budget or Plnd. Cost Percent Completed A 3.00 - 15000 100 B 1.00 A
Data for a project is shown below:
| Activity | Duration (months) | Precedence | Budget or Plnd. Cost | Percent Completed |
| A | 3.00 | - | 15000 | 100 |
| B | 1.00 | A | 5000 | 0 |
| C | 2.00 | A | 10000 | 100 |
| D | 3.00 | A | 21000 | 50 |
| E | 2.00 | C | 32000 | 0 |
| F | 1.00 | C | 5000 | 0 |
| G | 1.00 | C | 5500 | 0 |
The project started on June 1st. The project has a planned duration of 7 months.
Data below are planned cost and actual cost (spent) from June to November:
| Month | Planned cost | Actual cost |
| June | 5000 | 8000 |
| July | 5000 | 8000 |
| August | 5000 | 5000 |
| September | 5000 | 5000 |
| October | 12000 | 12000 |
| November | 23000 | 12000 |
- Compute critical ratio?
- Based on current cost performance level, what is the estimated cost in completing the project?
- Based on current schedule performance level, how much more time (in months) is needed to complete the project?