Question: Data for six weeks from a carpeting crew is as follows: Week Crew Size Yards Installed 1 4 96 2 3 72 3 4 92
Data for six weeks from a carpeting crew is as follows:
| Week | Crew Size | Yards Installed |
| 1 | 4 | 96 |
| 2 | 3 | 72 |
| 3 | 4 | 92 |
| 4 | 2 | 50 |
| 5 | 3 | 69 |
| 6 | 2 | 52 |
Compute the labor productivity (= yards installed per crew member) for each of the six weeks. Which week has the highest productivity?