Question: Data for the following activities for The MSVU Project are below. The times are in weeks. The critical path for the project is A-D-H-I-J-
Data for the following activities for The MSVU Project are below. The times are in weeks. The critical path for the project is A-D-H-I-J- K. The expected completion time is 36.5 weeks. Determine the probability of completing the project by the 38 week deadline. Ensure you show all your work including the variance calculations. Activity Optimistic Time Most Likely Time Pessimistic Time A 17 19 14 B 2 2 18 C 18 12 16 ID |3 15 10 4 6 18 F 6 8 10 IG 2 3 14 H 2 2 18 16 18 16 14 16 14 K 12 5