Question: Data on expected time and variance for each path on a project to produce widgets is provided below. All task times on the project was
Data on expected time and variance for each path on a project to produce widgets is provided below. All task times on the project was recorded in weeks. Using the data, calculate the probability of completing the project in 35 weeks. (Record your answer as xx.xx, so for example an answer should be recorded as 99.99 if the answer is 99.99%).
| Path Number | Path Expected Time | Path Variance (weeks) |
| 1 | 26.6 | 0.99 |
| 2 | 15.2 | 7.38 |
| 3 | 36.99 | 2.6 |
| 4 | 1.55 | 9.13 |