Question: Data on small maintenance project is given as in the table below. On completion, the project will give a return of $ 1 5 0

Data on small maintenance project is given as in the table below. On completion, the project will give a return of$150/day. Using time-cost trade-off method, how much would you like to compress the project for maximizing the return (ignore the Indirect Cost effect)? Show all calculations.
Activity
Depends on
Normal
Crash
Time (days)
Cost ($)
Time (days)
Cost ($)
A
-
8
700
6
900
B
A
4
400
3
500
C
A
5
600
2
900
D
A
3
625
2
775
E
B, C
6
400
6
400
F
B, C, D
8
500
6
700
G
C, D
11
1150
8
1300
H
D
7
800
5
950
I
E, G
5
350
4
600
J
F, G
8
750
6
950
K
G, H
4
420
3
580
L
H
9
925
7
1075
M
I, K,
6
350
4
670
N
J, K, L
5
860
2
1100
O
L, M, N
7
540
4
720

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!