Question: Data Table 1 . Route sheet for Part 1 ( P 1 ) Operation Time Resource No . Description Process [ min / / unit

Data
Table 1. Route sheet for Part 1(P1)
Operation Time Resource No. Description
Process [min//unit]
Setup [min//batch]
Description Code 1 Sawing 7.216 Power hacksaw M12 Rough milling 9.432 Milling machine M23 Finish milling 6.832 Milling machine M24
Drilling-boring-reaming- tapping
22.8120 Vertical milling center M35 Surface grinding 9.628 Surface grinder M46 Final inspection 5.818 Inspection bench M5 Demand =1200 units/month; Batch size =10 units (for both production and transportation)
Table 2. Route sheet for Part 2(P2)
Operation Time Resource No. Description
Process [min//unit]
Setup [min//batch]
Description Code 1 Milling base surface 4.832 Milling machine M22 Drilling-reaming 6.222 Upright drill press M63
Milling-drilling-reaming- tapping
20.6120 Vertical milling center M35 Surface grinding 8.328 Surface grinder M46 Final inspection 4.718 Inspection bench M5 Demand =1200 units/month; Batch size =10 units (for both production and transportation)
Table 3. Route sheet for Part 3(P3)
Operation Time Resource No. Description
Process [min//unit]
Setup [min//batch]
Description Code 1 Milling-centering 6.818
Milling and centering machine
M 72 Turning 7.634 Engine lathe M 83 Milling slots 3.832 Milling machine M 24
Drilling-chamfering- tapping
5.722 Upright drill press M 65 Contour milling 16.4120 Vertical milling center M 36 Final inspection 4.818 Inspection bench M 5
Demand =1200 units/month; Batch size =10 units (for both production and transportation)
Equipment selectionYou need to search machines listed in Tables 1-3 and find their dimensions and costs. Assume all machines have 90% efficiency with a 5% scrap rate. For personnel requirements, assume one operator can handle up to two units of the same machine type except for the inspection bench which needs one operator per unit. Material flow analysisObtain quantitative flow data from the given data. Material handling systemDecide the most appropriate type of material handling system for the facility. Search for data about the selected MHS, including speed and cost.
Data Table 1 . Route sheet for Part 1 ( P 1 )

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!