Question: Date: True or False ( 2 4 pts ) Answer the questions below related to the following schedule items: 1 . 2 . 1 -

Date:
True or False (24pts)
Answer the questions below related to the following schedule items:
1.2.1- Strip foundation wall forms
5.2- Structural Steel Installation @ Column Line A17-A19
9- Finishes
True or false:
Task "1.2.1- Strip foundation wall forms" is a level 1 task on the WBS.
a. True
b. False
True or False:
Task "9- Finishes" is a level 9 task on the WBS.
a. True
b. False
True or false:
Task "5.2- Structural Steel Installation" is a level 2 task on the WBS.
Multiple Choice (56pts)
Answer the following multiple-choice questions:
4. Activity D and Activity C have a shared predecessor of Activity B. Activity B has an Early Start date of Day 2, and a duration of 1 day. Which of the following is true?
a. Activity C begins before Activity D
b. Activity C begins on Day 4
c. Activity D begins on Day 3
d. None of the above
 Date: True or False (24pts) Answer the questions below related to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!