Question: Dave's earliest start ( ES ) and earliest finish ( EF ) are: table [ [ Activity , ES , EF ] , [

Dave's earliest start (ES) and earliest finish (EF) are:
\table[[Activity,ES,EF],[A,0,7],[B,0,6],[C,7,11],[D,7,9],[E,6,9],[F,6,12],[G,11,22],[H,12,19]]
Dave's latest start (LS) and latest finish (LF) are:
\table[[Activity,LS,LF],[H,15,22],[G,11,22^(TT)],[F,9,15^(TT)],[E,8,11],[D,13,15],[C,7,11],[B,2,8],[A,0,7]]
The slack times are:
ActivitySlackA0B2C0D
 Dave's earliest start (ES) and earliest finish (EF) are: \table[[Activity,ES,EF],[A,0,7],[B,0,6],[C,7,11],[D,7,9],[E,6,9],[F,6,12],[G,11,22],[H,12,19]] Dave's