Question: Days Activity Optimistic Most Probable Pessimistic Immediate Predecessors a 8 10 12 - b 6 7 9 - c 3 3 4 - d 10

Days
Activity Optimistic Most Probable Pessimistic Immediate Predecessors
a 8 10 12 -
b 6 7 9 -
c 3 3 4 -
d 10 20 30 a
e 6 7 8 c
f 9 10 11 b, d, e
g 6 7 10 b, d, e
h 14 15 16 f
i 10 11 13 f
j 6 7 8 g, h
k 4 7 8 i, j
l 1 2 4 g, h

1. Determine the expected time and variance for each activity. 2. Construct a network. 3. Determine the critical path. 4. Project completion time. 5. Draw the corresponding normal curve.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!