Question: Deadline: 0 5 . 0 3 . 2 0 2 4 EcoTech Inc. is a sustainable technology company based in Istanbul, Turkey, specializing in the

Deadline: 05.03.2024
EcoTech Inc. is a sustainable technology company based in Istanbul, Turkey, specializing in the production of three types of renewable energy systems: Solar Panels, Biofuel Generators, and Hydroelectric Generators. The company's factory is equipped to manufacture these products according to demand forecasts provided by the Sales Department for the next four months, as detailed in Table 1 of the case study.
Months Solar Panels Biofuel Generators
Hydroelectric Generators
October 320160350
November 510210110
December 360260220
January 430330630
At the beginning of October, EcoTech Inc. employs 24 workers at its factory, each capable of working 100 hours per month during regular hours at a rate of $30 per hour. Additionally, workers can work up to 50 hours of overtime per month at a rate of $60 per hour. The company has the option to hire additional workers as needed, but incurs legal costs of $500 per new hire, with a monthly recruitment budget of $5,000 set by the Human Resources Department.
In addition to in-house production, EcoTech Inc. has the option to outsource a portion of the monthly production of Biofuel Generators to a subcontractor. Any excess production beyond monthly demand can be stored in inventory for future use, with unit inventory holding costs calculated based on a monthly interest rate of 0.4%. The warehouse capacity at the factory is limited to 500 units for the total inventory of the three products. At the beginning of October, no panel or generators are held in the inventory.
If a months delivery cannot be fulfilled, backordering is permitted, allowing for late delivery of demand with additional costs. However, all demand must be satisfied by the end of January.
For Solar Panels, Biofuel Generators, and Hydroelectric Generators, unit manufacturing costs, unit subcontracting costs, backordering costs, and labor requirements are provided.
Solar Panels Biofuel Generators
Hydroelectric Generators
Manufacturing Cost ($ per unit)360003000032000
Subcontracting Cost ($ per unit) N/A 40000 N/A
Backordering Cost ($ per unit per month)225018002000
Labor Requirement (hours per unit)1066
EcoTech Inc. aims to determine a monthly production plan for the three renewable energy systems and a workforce plan for the four-month period, with the objective of minimizing total costs. As consultants hired by the company,
a) Formulate the problem as a linear programming (LP) model. Keep in mind that the model may involve non-integer numbers of workers and vehicles.
b) Utilize Excel Solver to solve the LP model, as the company lacks access to other optimization packages.
c) Conduct a comprehensive sensitivity analysis and compile the results into actionable suggestions for presentation to the management of EcoTech Inc. Suggestions may include considerations such as implementing a salary increase in January or negotiating terms with subcontractors to optimize costs and improve efficiency.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!