Question: Dear expert, I need the solution for question 3 and 4 . If you are expert then take the question , do not waste my
Dear expert, I need the solution for question 3 and 4 . If you are expert then take the question , do not waste my question , solution already available , but do not copy paste.. i need perfect answer for question 3 and 4 .

2. The footings of a building can be completed in four connective sections. The activities for each section include (1) digging, (2) placing steel, and (3) pouring concrete. The digging of one section cannot start until that of the preceding section has been completed. The same restriction applies to pouring concrete. Develop the project network using an Activity on Node representation.
(25 points)
3. In Problem 2, suppose that after digging all sections, plumbing work can be started but only 20% of the job can be completed before any concrete is poured. After each section of the footings is completed, the remaining plumbing work can be started provided that the preceding 20% portion is complete. Construct the project network using an Activity on Node representation.
(25 points)
Question: 04 :

Remember that question 3 and 4 . Thanks
1. The widening of a road section requires relocating (reconductoring) 1700 feet of 13.8-kV overhead primary line. The following table summarizes the activities of the project Construct the associated project network. Notation Activity Description A B Predecessor(s) Duration (days) 1 A 1/2 D E F G H 1 J K L M N 0 P Q R S Job review Advise customers of temporary outage Requisition stores Scout job Secure poles and material Distribute poles Pole location coordination Re-stake Dig Holes Frame and set poles Cover old conductors Pull new conductors Install remaining material Sag conductor Trim trees De-energize and switch lines Energize and switch new line Clean up Return material to stores A A CD E D G H FI F1 J.K L L D B.M,N,O P Q 1 1 1/2 3 3 1/2 1/2 1/2 3 4 1 2 2 2 2 1/9 1/2 1 2 4. Construct an AOA and AON network for a project comprised of activities A to P that satisfies the following precedence relationships: a. A, B, and C, the first activities of the project, can be executed concurrently. b. D, E, and F follow A. c. I and G follow both B and D. d. H follows both C and G. e. K and L follow I. f. J succeeds both E and H. g. M and N succeed F, but cannot start until both E and H are completed. h. O succeeds M and I. i. P succeeds J, L, and O. j. K, N, and P are the terminal activities of the projectStep by Step Solution