Question: Dear Tutor, I need your help and the steps for the following question: Question 1 Draw an Activity Network Diagram for Project D based on
Dear Tutor,
I need your help and the steps for the following question:
Question 1
Draw an Activity Network Diagram for Project D based on the task table below:
| Activity | Predecessor | Duration (Days) | Relationship |
| A | - | 15 | - |
| B | A | 4 | FS |
| C | A | 7 | FS |
| D | C, H | 20 | FS |
| E | J | 13 | FS |
| F | D, L | 14 | FS |
| G | E, F | 5 | FS |
| H | B | 8 | FS |
| J | D | 9 | FS |
K A 8 FS
----------------------------------------------------------------------------------------------------------------------
L K 15 FS + 5
---------------------------------------------------------------------------------------------------------------------
Question 2
Identify the Critical Path(s) and the duration.
Question 3
What is the impact to the Critical Path if Task L was delayed by 10 days and Task G was completed early by 2 days? Explain your answer.
Thank you very much for your help.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
