Question: Dear Tutor, I need your help and the steps for the following question: Question 1 Draw an Activity Network Diagram for Project D based on

Dear Tutor,

I need your help and the steps for the following question:

Question 1

Draw an Activity Network Diagram for Project D based on the task table below:

Activity Predecessor Duration (Days) Relationship
A - 15 -
B A 4 FS
C A 7 FS
D C, H 20 FS
E J 13 FS
F D, L 14 FS
G E, F 5 FS
H B 8 FS
J D 9 FS

K A 8 FS

----------------------------------------------------------------------------------------------------------------------

L K 15 FS + 5

---------------------------------------------------------------------------------------------------------------------

Question 2

Identify the Critical Path(s) and the duration.

Question 3

What is the impact to the Critical Path if Task L was delayed by 10 days and Task G was completed early by 2 days? Explain your answer.

Thank you very much for your help.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!