Question: dec 19 QUESTION 3 A dam construction project requires nine (9) activities as per the following table. TASK PREDECESSOR(S) TIME (WEEKS) A B C D

dec 19

dec 19 QUESTION 3 A dam construction project requires nine (9) activities

QUESTION 3 A dam construction project requires nine (9) activities as per the following table. TASK PREDECESSOR(S) TIME (WEEKS) A B C D B 1 m B F C,D E F.G a) Draw the appropriate PERT diagram. (3 marks) b) Calculate the earliest start time and latest start time for each event. (4 marks) c) Calculate the project completion time. (1 mark) d) Identify the critical path and critical activities of the project. (2 marks) e) Calculate the total float and the free float for activity D. (2 marks) f) Compute the project completion time if activity F is delayed by 5 weeks. (1 mark)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!