Question: decision support tool Remaining Time: 41 minutes, 22 seconds. QUESTION COMPLETION STATUS: Consider the following project details and estimates: Activity Crash cost ($) A B
Remaining Time: 41 minutes, 22 seconds. QUESTION COMPLETION STATUS: Consider the following project details and estimates: Activity Crash cost ($) A B D E F G Normal Crash time time (days) (days) 15 12 19 14 9 5 6. 5 14 9 9 6 8 3 Total direct cost Normal cost (5) 4 500 4 000 2 500 1 700 4 300 2 600 1 800 21 400 5250 4500 4 500 1 860 5350 3440 3400 28 300 The network diagram for the project is shown below: 15 79 o In addition to the direct activity costs there are indirect project costs of S275 per day. What is the most cost-effective time in which to plan to complete the project? O. 27 days 23 days Ob