Question: Decrease the project completion time by 5 days than the normal time for the following project and complete the following table. 2 5 days 10

Decrease the project completion time by 5 days

Decrease the project completion time by 5 days than the normal time for the following project and complete the following table. 2 5 days 10 14 $300 $100 5 6 $250 Actual Crash cost 1 Activity 1-2 1-3 2-4 2-5 3-4 4-5 $300 $200 Normal Activity time (Days) 5 10 14 10 8 6 10 3 Activity Crash Activity Crash cost/Days time (Days) 300 2 200 8 100 300 400 250 9 5 4 Actual Crash time (Days) 8 $400 6 4 Total crash cost