Question: Define safety stock level by using the mathematic formula, the purchasing lead time is 17 weeks and you want to have a service level of
Define safety stock level by using the mathematic formula, the purchasing lead time is 17 weeks and you want to have a service level of 98%

Month Ordered 1 23 456 7 8 9 10 11 12 81 56 79 21 47 101 50 65 108 45 60 82 Delivered Inventory level 64 67 75 82 96 99 87 86 84 92 80 78 79 56 71 20 47 68 50 65 105 45 59 79
Step by Step Solution
There are 3 Steps involved in it
Solution Heres the calculation of safety stock level using the mathematical formu... View full answer