Question: Define the Project Plan the Project Control the Project Example: . Project Scope . Activity Owners . Hold regular Reviews 4. Case Study: Question: A

Define the Project Plan the Project Control the Project Example: . Project Scope . Activity Owners . Hold regular Reviews 4. Case Study: Question: A construction project needs to complete three activities before the construc tion can begin. Activity A, takes 8 weeks, activity A, takes 9 weeks, and activity A, takes 10 weeks, However, the activity times are somewhat uncertain-sometimes they happen up to four weeks faster, while at other times they take four weeks longer. The project manager suggests starting A, two weeks late because the activity is not on the critical path, and so this delay will not impact the project completion time. What is your reaction to this suggestion