Question: Delaying activities on the critical path Will delay the project Will create an additional critical path Aren't a concern, it's all the paths we care
Delaying activities on the critical path
Will delay the project
Will create an additional critical path
Aren't a concern, it's all the paths we care about
Aren't a concern, it's the slack time we care about
Is a great way to get more resources allocated to a project