Question: Delta will need to build 8 7 5 6 computers for a given order. In 2 0 1 9 , the company's demand is expected

 Delta will need to build 8756 computers for a given order.

Delta will need to build 8756 computers for a given order. In 2019, the company's demand is expected to increase by 5%. The company's carrying cost for the projects has been established at 9%. The company has $5.5 million dollars in inventory which is an increase from last year. The CFO has indicated that the ordering cost per order is $3. Southwest's sales were $1,790,505 in the last quarter of 2018. The company is expected to increase sells by 19% over the next two years. The cost for all components to build the computers is $52. The expect sell price for each units is $725. Southwest's total assets is estimated to be $21.6 million dollars and expected to grow in coming years.
What is Southwest's EOQ?
.
A).115.95
B).105.59
C).105.05
D).105.95
E).115.59
How many orders should they place each year?
.
A).77.3
B).87.01
C).83.46
D).85
E).82.64
Southwest operates for 300 days out of the year. How many days apart should they place an order?
.
A).3.11
B).3.63
C).3.71
D).8.63
E).19.61
In 2019, the company's demand is expected to increase by 5%. The

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!