Question: Demand = 10 units per day Lead time = 5 days Safety Stock = 5 units Kanban container hold = 3 parts How many Kanbans
Demand = 10 units per day
Lead time = 5 days
Safety Stock = 5 units
Kanban container hold = 3 parts
How many Kanbans should you use?