Question: Demand = 2000, optimal order quantity level =200, what is the expected days between orders for a 250-day working year Question 19 options: 10 20

Demand = 2000, optimal order quantity level =200, what is the expected days between orders for a 250-day working year

Question 19 options:

10

20

25

50