Question: Demand durinf lead time is historically about 9 4 . It is normally distributed with a standard devaition during lead time of 1 1 .

Demand durinf lead time is historically about 94. It is normally distributed with a standard devaition during lead time of 11. They will use a stockout risk of three precent. What is the reorder point, including the safety stock