Demand for a product is relatively constant at 5 units per day. Lead time for this product is normally distributed with a mean of 20 days and a standard deviation of 4 days.

(a) What reorder point provides an 80 percent service level?
(b) What reorder point provides a 90 percent service level?
(c) If the lead time standard deviation can be reduced from 4 days to 1, what reorder point now

provides 90 percent service? How much is safety stock reduced by this change?