Question: Demand for the bird feeder is normally distributed with a mean of 18 units per week and a standard deviation in weekly demand of 5

Demand for the bird feeder is normally distributed with a mean of 18 units per week and a standard deviation in weekly demand of 5 units. The lead time is 2 weeks, and the business operates 52 weeks per year. The Q system called for an EOQ of 75 units. What is the target inventory level for a Psystem with 98 percent cycle-service level? Round your answer to your nearest integer. Group of answer choices 108 25 16 124 133