Question: Describe a mathematical model for the following scheduling problem. Given tasks T1, T2, . . . , Tn, which require times t1, t2, . .
Describe a mathematical model for the following scheduling problem. Given tasks T1, T2, . . . , Tn, which require times t1, t2, . . . , tn to complete, and a set of constraints, each of the form "Ti must be completed prior to the start of Tj," find the minimum time necessary to complete all tasks.